Net Metering Bihar me kaise hota hai? (Full Process, Documents, Time & Approval Guide 2026)
Agar aap solar system lagwane ka plan bana rahe hain, to sabse important cheez hai Net Metering.
Bahut log confuse rehte hain ki solar lagane ke baad meter kaise change hota hai, approval kaise milta hai aur kitna time lagta hai.
Is blog me hum aapko Bihar ke liye complete step-by-step net metering process batayenge.
⚡ Net Metering kya hota hai?
Net Metering ek system hai jisme:
- Aapka solar system bijli banata hai
- Jo extra bijli hoti hai wo grid me chali jati hai
- Aapka bijli bill adjust ho jata hai
👉 Matlab aap bijli bech bhi sakte hain aur use bhi kar sakte hain.
🔄 Bihar me Net Metering ka Process
- Step 1: Solar system install karwana
- Step 2: DISCOM me application submit karna
- Step 3: Site inspection hota hai
- Step 4: Approval milta hai
- Step 5: Normal meter hata kar net meter lagaya jata hai
📄 Required Documents
- Electricity bill copy
- Aadhaar card
- Mobile number
- Property proof
- Solar system details
⏱️ Kitna time lagta hai?
- Application to approval: 7–15 din
- Meter change: 5–10 din
👉 Total process approx 15–25 din me complete ho jata hai.
💰 Net Metering ka fayda
- Bijli bill 70%–100% tak kam
- Extra unit ka adjustment
- Long-term saving
⚠️ Important Tips
- Only certified vendor se installation karaye
- Proper documentation karein
- Subsidy aur net metering ek saath apply karein
📞 Free Net Metering Support Bihar
Agar aap Bihar me solar lagwana chahte hain to hum aapko complete support (installation + net metering + subsidy) provide karte hain.
Ark Urja Machinery (OPC) Private Limited
📍 Begusarai, Bihar
📞 Call / WhatsApp: 8809514296
✅ Conclusion
Net Metering ke bina solar system ka full benefit nahi milta.
Isliye hamesha solar lagwate waqt net meter process ko samajhna zaruri hai.
👉 Sahi process follow karne se aapka bijli bill almost zero ho sakta hai.